| Aviation Test Stand |
Snecma Moteurs![]()
The detailed objective of the project was to be able to set up the test beds within half a day instead of a week. In addition, the precision with which the siren (a highfrequency airflow generator) could be positioned was to be improved. It was also essential for Snecma Moteurs to have the option of adjusting the position of the siren quickly during the tests, with the guarantee that the position could be reproduced in the case of tests on several identical blades. The Bertrandt team suggested the following approach: drawing up a specification document followed by a functional analysis, demonstrating the technical solutions and making comparisons between them. Snecma Moteurs accepted the bid from Bertrandt Bièvres in the middle of 2000.
Preliminary design: overall cost estimate At the request of the development department of Snecma Moteurs, Bertrandt Bièvres produced a preliminary design of the solution that had been chosen. The purpose was to define in more detail the proposed technical solutions and to specify the costs and the timeframe involved in this option. Project management: from concept study to installation Bertrandt Bièvres received the go-ahead to start developing and manufacturing the test bed in May 2002. The scope of the project involved Bertrandt Bièvres acting as general contractor and taking responsibility for the project management, the concept study, the manufacturing, assembly, installation and adjustment at the Snecma Moteurs site. Bertrandt Bièvres collaborated with partners on the electronics system and on the production of the test bed. The test bed was ready for delivery on schedule in October 2002. It weighed 1.4 tonnes in total, 800 kg of which was made up by the moving parts. At the request of Snecma Moteurs, the delivery was planned for 2003. The decision to delay delivery followed a joint initial acceptance procedure, which involved demonstrating the functional compliance of the test bed. The test bed was delivered, installed and commissioned in February 2003, a process that took two days. After this, the machine was presented to the Snecma Moteurs team in order to allow them to become familiar with its operation. After Snecma Moteurs had tested the test bed for a month, Bertrandt carried out the final acceptance procedure. At the end of the project, Snecma Moteurs was full of praise for the entire team and the results of their work. Future prospects As a result of the successful implementation of the project, Bertrandt Bièvres was awarded additional follow-up projects. Bertrandt very much appreciates Snecma Moteurs’ confidence in its competence and flexibility and looks forward to future collaboration in the field of test bed engineering. Thanks go to all those who have contributed to this positive development and to the success of this intriguing engineering project. |
|||||||||||



